BCS Services — Concrete, Masonry, Excavation
BCS SERVICESConcrete · Masonry · Excavation
Prepared for AtomVie Global Radiopharma10 Aeropark Blvd · 1,300 sq ft
Priority — Emergency Scheduling
10 Aeropark Blvd commercial facility front elevation

Emergency Sod Repair Proposal

Emergency Sod Repair & Front Grounds Restoration

10 Aeropark Blvd, Hamilton, Ontario

Prepared for AtomVie Global Radiopharma · Submitted by BCS Services

Total Investment$7,800.001,300 sq ft at $6.00 per sq ft · Removal, disposal, topsoil, sod and finishing included. Taxes extra.

Overview

Restore the frontage. Quickly, and properly.

The front grounds at 10 Aeropark Blvd currently carry construction debris, exposed gravel and disturbed fill across the entrance approach, parking perimeter and roadside frontage. This proposal covers a complete emergency restoration of those areas: everything unsuitable is removed and disposed of, new topsoil is placed and graded, and fresh sod is installed to return the property to a clean, presentable commercial standard.

Measured Area1,300 sq ft

Front entrance approach, parking perimeter margins and roadside frontage strip.

Unit Rate$6.00 / sq ft

All-inclusive: removal, disposal, topsoil, sod, grading and site finishing.

PriorityEmergency Schedule

Released for immediate scheduling on written approval from site management.

Site Conditions

The areas included in this scope.

Photographed on site. Select any image to view it full screen.

10 Aeropark Blvd — front elevation, main entrance approach and perimeter landscape areas included in this scope.
Site Overview

10 Aeropark Blvd — front elevation, main entrance approach and perimeter landscape areas included in this scope.

Scope of Work

What is included, and why it matters.

Each stage is sequenced so the finished turf sits on prepared ground, not on top of the existing problem.

Debris Removal & Disposal

  • Clear all existing construction debris from the affected areas
  • Strip and remove existing dirt, gravel and unsuitable fill
  • Load, haul and legally dispose of all removed material offsite
  • Protect adjacent asphalt, curbs and walkways during removal

Grade & Topsoil Preparation

  • Rough grade the exposed subgrade for positive drainage away from the building
  • Supply and place new screened topsoil to a consistent finished depth
  • Fine grade, rake and roll to a smooth, uniform surface
  • Confirm transitions to curbs, sidewalks and asphalt sit flush

New Sod Installation

  • Supply and install fresh nursery-grade sod across 1,300 sq ft
  • Tight-butted joints, staggered rows and trimmed edges at all borders
  • Roll installed sod for full root-to-soil contact
  • Initial watering and turf care instructions provided at handover

Site Finishing & Cleanup

  • Finish the front areas of the property for a clean, presentable appearance
  • Sweep and wash down adjacent hard surfaces
  • Remove all equipment, materials and waste at completion
  • Final walkthrough with the site contact before demobilization

Investment Summary

One measured scope. One clear rate.

Pricing is based on 1,300 measured square feet at $6.00 per square foot, inclusive of debris removal, disposal of existing dirt and gravel, new topsoil, new sod and finishing of the front property areas. Applicable taxes are additional.

Total$7,800.00Plus applicable taxes
ItemDescriptionQuantityUnitTotal
Emergency Sod Repair — Front GroundsRemoval and disposal of existing debris, dirt and gravel; supply and placement of new topsoil; supply and installation of new sod; grading and finishing of the front property areas.1,300sq ft$7,800.00

Why BCS Services

Clear scope. Clean execution.

Emergency Response

Scheduled ahead of standard queue to restore the property frontage quickly.

Built Properly

Proper removal, grading and topsoil depth beneath every square foot of new turf.

Clear Scope

One measured area, one unit rate, no hidden allowances or surprise extras.

Presentable Result

A clean, commercial-grade frontage suitable for client and regulatory visits.

Timeline

1–2 days total. Scheduled for August 19–21.

A compact, sequenced schedule designed to restore the frontage quickly while keeping the site safe and presentable during business hours.

01

Approval

Written approval from AtomVie site management by August 18 releases the crew for August 19 mobilization.

02

Day 1 — Mobilize & Remove

Crew and disposal bin arrive first thing August 19. Debris, dirt and gravel stripped and hauled offsite the same day.

03

Day 1 — Topsoil & Prep

New topsoil placed, graded and rolled before close of day, ready for sod first thing the following morning.

04

Day 2 — Sod & Finish

Fresh sod installed across the 1,300 sq ft area, edges trimmed, sod rolled and adjacent hard surfaces cleaned.

05

Handover

Final walkthrough, watering instructions and site demobilization by end of day August 20 — with August 21 held as a buffer if needed.

Approval

Ready to restore the frontage.

On written approval, BCS Services will schedule this emergency sod repair at 10 Aeropark Blvd and confirm the mobilization date with the AtomVie site contact. Workmanship is backed by our standard commercial warranty.

Proposal Summary
Area1,300 sq ft
Total$7,800.00